31 May 2021 18:16 #1 by ffornarini
We have a problem exporting and reopening a project (gantt) from Projeqtor.
The duration of the tasks don't match.
Example on the first 2 tasks on battached pictures :
- 'Input data definition ' task : 3 days on Projeqtor goes to 0.6day on MS project.
- "Product design" task : 20 days on projeqtor goes 4 days on MS project.
 


Have you ever seen this issues? Do you have a solution to are able to open the datas on MS project with the correct task durations.

Thanks for your help.
Attachments:

Please Log in or Create an account to join the conversation.

More
04 Jun 2021 14:39 #2 by babynus
I guess it is because MS-Project does not manage Pools.
Moreover, you are using a "unique resource" planning for the pools.
MS-Project does not understand and uses full pool capacity...

This is a limit of export/import with tools than don't plan the same way.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.