Hello,

i notice on my projects (and see the same on DEMO) that, if names are long (for project or milestone) Gantt view is difficult to read and even more for Portfolio.

Example :
 

 

Is it possible that, for portfolio, milestone are put on a différent line, so project line remain visible and milestone line is clear too. If milestone name or project name are too long, user may have to adjust it, but it keep clear for a long project name and milestone.

Expect to be clear.

Regards,
Attachments:

Please Log in or Create an account to join the conversation.

More
26 Apr 2024 15:27 #2 by maxca
Hello,
Ticket recorded #8470  
Thank you for your feedback.

Maxca

Please Log in or Create an account to join the conversation.

More
28 Apr 2024 19:59 #3 by babynus
Is it possible that, for portfolio, milestone are put on a différent line, so project line remain visible and milestone line is clear too
Sure NO : it was a frequent request to see the milestones on the project line, and it was a hard word to set this as it is.
But milestone names on the Gantt part should not be displayed on Portfolio (showing milstones name on Gantt chart is a new feature)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.