09 Apr 2013 16:36 #1 by magicangel
Maybe you could add new kind of reporting with:
- earn value (EV)
- planned value (PV)
- actuel cost (AC)



and maybe add new indicator on the project area with
- Schedule variance (SV)= EV - PV
- Schedule performance index (SPI)= EV/PV

what do you think?
Attachments:
The following user(s) said Thank You: JCDe

Please Log in or Create an account to join the conversation.

More
09 Apr 2013 19:53 #2 by babynus
Request recorded as Ticket #1044.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
10 Apr 2013 09:50 #3 by climb4fun
Hi all,

I support this request as well. Might be good, to have this EVA based on cost and on mandays / hours.

Klaus

Please Log in or Create an account to join the conversation.

More
11 Apr 2013 22:13 #4 by JCDe
I support this request as well.

this is a very good indicator.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.047 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.